Amazon faces obstacles in expanding data center footprint in Europe due to delays in power grid links
Linking to the European transmission system can take as long as 7 years — contrasting with the roughly 2 years required to construct a data center facility, said Pamela MacDougall, head of energy markets and regulation for EMEA at Amazon Web Services